Current Projects

Bridge Road Reconstruction 

Update – June 5, 2020

Crews will be completing the final touches on the bridge railings.  Restoration of terrace areas continues.  Small sections of pavement striping remain.  Otherwise this project is almost complete and the road is fully open.

Plan drawings, Click Here
City of Madison has assessments for this project for nearby City of Madison property ownerssee here.

McKenna Road Reconstruction

 - 2020

Updated - June 5, 2020

Crews are installing sanitary main and water & sanitary laterals as they head South on McKenna.  Watermain is installed and live.  Two watermain connections need to be completed in the intersections of McKenna and Greenway which will cause a temporary shut down of water in the area.  Residents will be notified 48 hours in advance of the shutdown.  The roadway remains temporarily signed for no parking along McKenna between Maywood and Dean.  

Construction Schedule:

Sanitary sewer main installation - ongoing
Water and sewer lateral installation - ongoing

Construction Plans

Winnequah Road Pirate Island Bridge Replacement

Updated - April 22, 2020

The City of Monona has plans to replace the Winnequah Road bridge to Pirate Island in 2020.  The current bridge was constructed in 1960, and has a sufficiency rating of 8.6 out of 100.  Reconstruction plans call for the complete replacement of the bridge.  One lane will be open to residents during the construction.  During construction, the water main currently hanging from the bridge will be placed under the channel, just to the west of the bridge.  Engineering design was completed by MSA, led by Gregg Borucki.
View a presentation on reconstruction plans

2020 bids were denied due to over budget quotes.  Capital budgets will be amended in the Fall and this project will be rebid in the Spring of 2021.  



North Winnequah Park Lagoon Dredging and PCB Removal 

Updated - June 5, 2020

This project has wrapped up except some restoration items that still remain.

Construction Schedule:

Spring of 2020, 
Restoration and final landscaping.
For Plan Drawings, Click Here

​Atwood Ave. Road Reconstruction Planning and Design - 2022-2025


Updated - April 30, 2020

The project was not approved in the 2020 TIP for federal funding.  The project will apply for federal funds in 2022 for funding in 2024.

Visit the City of Madison project page for more information.

Pedestrian and Bicycle Improvements Plan

Monona City Council has accepted the plan and the information is posted on the City's Public Works page along with all supporting data and reports.  Ped and Bike Plan

US DOT Projects In Monona - 2019-2020

Beltline Hard Shoulder Project

WisDOT Project Page

​Beltline South Towne Overpass, On/Off Ramp Improvements
WisDOT Project Page